EBRD and NGOs go Head-to-Head over Mochovce
The European Bank for Reconstruction and Development's proposal to
finance the final construction on Units 1 and 2 of the Mochovce nuclear
power plant in the Slovak Republic is being hotly debated among
environmental NGOs and others in Central and Eastern Europe.
The following exchange of letters is a striking example of the
confrontation and cooperation happening between local NGOs and this
multilateral development bank.
There are two issues involved. The first issue is the role of the
EBRD's environmental guidelines. Many inside and outside the Region
think the project violates the EBRD's environmental guidelines "to
promote in the full range of its activities environmentally sound and
sustainable development." The Mochovce case is important because it is
the first time the EBRD has considered financing the construction of a
nuclear power plant.
The second issue is public participation. In compliance with EBRD
guidelines, a public participation process must take place before the
bank gives final approval for the project. Called "scoping meetings,"
the first public participation meetings were held in Bratislava and
Levice on 10 and 11 August. About 16 NGOs (from the Slovak Republic and
elsewhere) participated. The meetings are to "allow the public and
other parties to raise issues which should be addressed in the
environmental assessment and to discuss arrangements for further pubic
participation," according to the EBRD's Environmental Procedures.
What follows is a point-counterpoint exchange. The statements are
excerpts from three letters: (1) a letter the NGOs wrote to EBRD
President Jacques de Larosiere, (2) President de Larosiere's response,
and (3) Global 2000's response to his conclusion. The first NGO letter
criticizes the EBRD's role in the project, including the way the bank
is handling the public participation process.
NGO Introduction:
22nd August 1994
Dear Mr. Jacques de Larosiere,
On the 10th of August a meeting was held in Bratislava between the
project sponsors for the completion of units 1 and 2 of the Mochovce
nuclear power plant and selected environmental NGOs. At the conclusion
of this meeting, the environmental NGOs present felt it was necessary
to write to you to convey our strong sense of disappointment, confusion
and frustration with this meeting and the public participation process
and environmental assessment of the Mochovce project. We would like to
emphasize in particular four major concerns.
EBRD Introduction:
30 August 1994
Dear Mr. Frogatt,
Thank you for your letter which I studied with great interest. I
attach great importance to your comments, and am pleased to reply to
your main points below.
Your letter addresses several key issues concerning the Mochovce
project and in particular the preparations for, and conduct of, the
scoping meetings, organized by the Project Sponsors, that were held in
Bratislava and Levice on 10 and 11 August 1994. As you know, in line
with the Bank's Environmental Procedures, the primary objectives of the
scoping exercise were to review with Non Governmental Organizations
(NGOs) and other interested parties the Terms of Reference for the
environmental assessment of the project, and to discuss with these
parties the proposed public participation program.
Because of the exceptional and unusual nature of this projectÑthe
completion of a nuclear power plantÑ, and the importance the Bank
places on effective public consultation, the Bank has hired a public
participation auditor to provide staff and Board Directors with an
independent view on the implementation by the Project Sponsors of
EBRD's public participation procedures. The auditor attended the
scoping meeting, and reported that 32 representatives from 16 NGOs
participated. The auditor will draft a report on all phases of the
public consultation process on the Mochovce project, which will be made
publicly available by the Bank, should the project be presented to the
EBRD Board of Directors.
First NGO Point:
The stated intent of the project sponsors that they will not release
full documentation of studies related to the project will make a farce
of the EBRD's desire to have an open and constructive environmental
assessment and public participation process. The reports and
information about nuclear safety and least-cost analysis in particular
are critical elements of the decision-making process with respect to
completion of units 1 and 2 at Mochovce. Failure to make these reports
available will irreparably damage the public's confidence in the
fairness and openness of the process and will make it impossible for
the public to have confidence in the decisions that will be made about
the most appropriate way of meeting the energy needs of Slovakia.
EBRD Response:
You correctly state that EBRD wishes to have "an open and constructive
environmental assessment and public participation process." The Project
Sponsors, of course, will release all information on the project to the
public that is required by the Bank's Environmental Procedures.
Accordingly, the Environmental Impact Assessment Report will be made
available to the public, at a date to be disclosed in the coming weeks
by the Project Sponsors.
In addition, subject to non-objection from the Slovak authorities, the
Bank will release, through the Project Sponsors, a report on a
least-cost analysis of the project. This report was commissioned by
the Bank to reflect the requirements of the Bank's Energy Operations
Policy, recently approved by the Board of Directors. The Policy states
that the Bank should focus "on projects that rank high in priority as
part of a long-term least-cost plan for the [energy] sector." Please
note that according to Bank procedures, public release of this document
is not mandatory and that I have authorized its release on an
exceptional basis.
You request that the Project Sponsors publish all available
information related to safety. Full disclosure of pre-operation safety
cases is not required in most European countries, nor by the Bank's
procedures. However, information regarding safety, whose release would
not represent a security risk to the plant, will be included in the
final EIA report. In addition, we would not oppose release of
additional safety information, if so directed by the Government of the
Slovak Republic.
Second NGO Point:
The current intent of the project sponsors to exclude an examination
of alternatives to Mochovce in the environmental assessment is a grave
error. Examination of alternatives which may more effectively, more
safely, and in a less environmentally damaging way meet the electrical
energy needs of Slovakia are necessary. The failure to examine
alternatives, from an environmental perspective, is in direct
contradiction to the Bank's Environmental Procedures and the
Environmental Impact Assessment law for Slovakia, which will come into
force on September 1st, 1994.
EBRD Response:
I fully understand your request that the Environmental Impact
Assessment should include a study of the alternatives to the completion
of the Mochovce facility to international safety standards. However,
because a key conditionality to the project is that it must be
demonstrated to be the least-cost option, the first step is indeed to
examine alternatives from an economic standpoint. If the least-cost
study indicates that there is a practical, realistic, and implementable
alternative to the completion of Mochovce Units 1 and 2, then the
environmental impact assessment will be extended to incorporate this
alternative.
Third NGO Point:
There has been confusion and insufficient time for NGOs to comment
on the official scoping of the Environmental Impact Assessment, the
present draft only allowed 7 days of comment for selected NGOs. Past
scoping documents were later classified as "unofficial" by Bank staff,
however, it appears that no additional period for comment will be made
available.
EBRD Response:
You raise several interesting points regarding public comments on
the project to date. The Project Sponsors have already incorporated many
NGO comments into the terms of reference of the EIA, which the Bank and
the Project Sponsors received over a period of months, starting in
January 1994. The Bank procedures do not actually require a second
phase of comment time to review Terms of Reference after they have been
amended as a result of NGO comments. I understand that these comments
and their inclusion or non-inclusion into the final terms of reference,
were actually debated at the August scoping meetings.
Fourth NGO Point:
The present intention of the project sponsors to limit public
meetings on this issue to Slovakia is unacceptable. Hundreds of NGOs
and individuals from throughout Europe have indicated their interest in
participation in the public participation program. Failure to provide
opportunities for their views to be publicly known will undermine the
fairness and completeness of the process. Open discussions such as
those recommended by NGOs have been strongly supported by the
Environmental Advisory Council (ENVAC) of the Bank. It is therefore
necessary to ensure that additional hearings are provided in
neighboring lands.
EBRD Response:
It is my understanding that Project Sponsors have agreed to respond
positively to requests for additional public meeting in Slovakia's
neighboring countries, providing that the relevant governments make the
request. This would seem to be a suitable solution.
Additional Point:
In addition to these major points discussed above the participants
at the Bratislava meeting would like to express to you their severe
disappointment that no representatives of the Bank were present at the
meeting. This increased considerably the confusion about the process
shared by both NGOs and other participants.
EBRD Response:
Concerning the lack of EBRD representation at the scoping meetings,
we understand your disappointment but we ensured that the public
participation auditor attended both meetings. We have transmitted his
comments and suggestions to the Project Sponsors. You must keep in
mind, however, that while our staff may assist Project Sponsors with
advice, or act as observers, it is ultimately the work of the Project
Sponsors that will be judged by the EBRD Board of Directors. Indeed our
procedures are clear that the implementation of public participation is
the Project Sponsors' responsibility, and not the Bank's.
NGO Conclusion, part 1:
Based on the concerns described above the NGOs present at the meeting
would request that the present process regarding the EIA and public
participation be stopped. This would allow for discussion with the
Bank, with the project sponsor, and with NGOs to ensure that the
process is correct. Failure to do so will seriously undermine the
validity of the whole process.
EBRD Conclusion, part 1:
Public participation and project preparation will continue as planned,
and we will continue to welcome your comments and input throughout the
process. If the Bank's Board of Directors is requested to make a
decision on this project, Directors will be able to review completed
project documentation along with the report of the public participation
auditor. The Board of Directors will ultimately judge compliance with
the Bank's policies and procedures.
NGO Conclusion, part 2:
In conclusion, we would like to reiterate that we are extremely
concerned about the inadequacy and openness of the public participation
process and environmental assessment for units 1 and 2 of the Mochovce
nuclear power plant project. Included in this letter we have identified
a number of recommendations for actions which we believe are necessary
to ensure the process is complete and fair. We would therefore ask you
to call a halt to the EIA and public participation process within the
project until you have considered these points and informed us as to
the actions you plan to take to correct the current difficulties. We
believe that a cessation of activities would ensure that the project
does not continue down an inappropriate and inadequate path.
Yours Sincerely,
Antony Frogatt,
Greenpeace International
On behalf of the following non-government organizations:
- Global 2000 [Austria]
- Austrian Ecology Institute
- Greenpeace Austria
- Greenpeace International
- Goncol Alliance [Hungary]
- Polish Ecological Club
- Greenpeace Slovakia
- Ipelska Unia [Slovakia]
- Society for Sustainable Living [Slovakia]
- Dubnicka Environmentalna Skupina [Slovakia]
EBRD Conclusion, part 2:
As recently stated by the Bank's management to our Environmental
Advisory Council, the issue is not, in the Bank's view, whether Units 1
and 2 at Mochovce will be commissioned. The units are 80-90% complete
according to the original Soviet designs. The plant could be completed
at a very low cost to the original Russian standards and be put in
operation within the next twelve months. If the plant were to be
completed to original Russian standards by the Slovak government on its
own, without any involvement of international institutions, then we can
safely assume that Bohunice VI, Slovakia's oldest nuclear units,
regarded as unsafe, would continue to operate beyond the year 2000. In
other words, Slovakia could well be faced with two Russian reactors
operating on Russian safety standards within 100 miles of international
borders, instead of one ex-Soviet reactor operating in compliance with
international safety standards. Of all alternatives to the completion
of Mochovce Units 1 and 2 to international safety standards, the option
of completing Mochovce to a low safety level, with no closure of
Bohunice VI, is certainly the most likely to happen, as funding for the
completion of these units could certainly be found. Indeed, this is why
the Bank considered funding this project in the first instance,
attaching as a key safety conditionality that Bohunice VI be shut down
as soon as units 1 and 2 at Mochovce are commissioned, and that the
project be part of the least-cost plan for the Slovak electricity
supply industry.
In conclusion, I note that this is probably the first time that such
extensive public consultation on an investment project has taken place
in any of our countries of operations. It is the EBRD's public
participation requirements, contained within the Bank's Environmental
Procedures, and approved by the EBRD Board of Directors in January
1992, which have initiated this process.
We will continue to be receptive to your comments and suggestions
regarding public participation on this project.
Yours Sincerely,
Jacques de Larosiere
THE BULLETIN * AUTUMN 1994